Contractor's Escape Before Completing Construction: Steps to Finish the Villa and Recover Your Rights
If the contractor has stopped work and disappeared before completing your house, villa or project, the correct legal route does not begin with filing a claim. It begins with three ordered steps: documenting what has actually been executed on site, then serving a formal notice through the Notary Public granting the contractor a reasonable period to resume the works, and then applying to the competent court to terminate the construction contract or to authorise you to entrust another contractor with completing the works at the first contractor’s expense, together with a claim for compensation for the damage suffered.
The gravest mistake project owners make is waiting indefinitely on promises to resume, or bringing a new contractor onto the site before the percentage of completion has been documented. Doing so destroys the evidence and makes it far harder for the expert to determine later what was executed and what was not. This article explains when a contractor is considered to be in default, how to document the situation, what your options are between rectification, termination and completion at the contractor’s expense, where the financial securities stand, and when the matter may turn into a criminal complaint.
When is a contractor legally considered to have stopped or absconded?
A delay of a few days or a slow pace of work is not enough to describe a contractor as being in breach of contract. The stoppage that produces legal consequences is a refusal to carry out the works without lawful cause and for a period that departs from the agreed programme, or leaving the site and withdrawing labour and equipment, or ceasing to respond to correspondence and notices, or a clear inability to continue after receiving payments. The more precisely the contract defines the execution period and payment milestones, the easier it is to establish the breach.
Step one: document the situation before doing anything else
Documentation is the foundation of the entire case, because the court measures the breach by what is established, not by what is alleged. This includes photographing the whole site with a clear date, taking inventory of the works executed and comparing them against the approved drawings and the contract items, collecting payment schedules, receipts and bank transfers, and preserving correspondence, messages and meeting minutes evidencing repeated promises to resume.
Alongside your own documentation, an application may be made for the appointment of an expert to establish the site condition, so that he inspects the site and issues an official report determining the actual percentage of completion and the state of the executed works. That report later becomes the pillar of the claim in determining what the contractor actually earned and what he received without entitlement.
Do not bring another contractor onto the site and do not carry out substantial changes before completing the documentation or obtaining authorisation from the court, because altering the site may deprive you of the ability to prove what the first contractor executed and what he left behind.
Step two: the notice through the Notary Public and the reasonable period
Before resorting to the courts, a formal notice is served on the contractor through the Notary Public setting out the breach and requiring him to resume and complete the works in accordance with the contract within a specified reasonable period. This notice serves a double function: it deprives the contractor of any argument that he was unaware, and it formally establishes that he has refused to perform after being put on notice, which is what the court relies upon when ordering termination or authorising completion at his expense.
The notice should ideally identify the contractual clauses breached, the date of the stoppage, the approximate percentage of completion, the amounts paid, and the period granted, with a warning that failure to respond will lead to legal proceedings and a claim for compensation and the agreed delay penalty.
Step three: your options before the court
The Civil Transactions Law obliges the contractor to complete the works in accordance with the terms of the contract. If it appears that he is performing the work defectively or contrary to the agreed terms, the employer may seek immediate termination where repair of the work is not possible. Where repair is possible, the employer may require the contractor to comply with the contract and correct the work within a reasonable period; if that period expires without correction, the employer may ask the judge to terminate the contract or to authorise him to entrust another contractor with completing the works at the first contractor’s expense.
Ending the contractual relationship together with a claim for the amount paid in excess of the value of the works actually executed, and for compensation for the damage resulting from the stoppage, such as the cost of alternative accommodation, re-tendering expenses and increases in material prices.
Obtaining a judgment authorising you to engage another contractor to complete the project, with the cost difference borne by the defaulting contractor and deducted from his entitlements or claimed separately. In practice this is usually the better option for a villa owner who wants his home finished rather than merely to win a case.
Financial securities: what actually protects your money
The strength of your position is determined not by the statement of claim alone but by the securities you retained. If the contract includes a performance bond or a bank guarantee, recourse may be had to it in accordance with its agreed terms. If the contract provides for a retention percentage on each payment, that is the first source from which completion cost differences are deducted. And if the contractor has fallen behind on a milestone corresponding to a due payment, the employer may withhold that payment on the basis of the defence of non-performance, provided the contractor is notified in writing.
Where the contract stipulates a specific delay penalty for each day or week of delay, it is a contractual provision that may be invoked before the court, and the court retains its power to assess whether the penalty is proportionate to the actual damage.
The role of court-appointed expertise
In most cases the court appoints an engineering or accounting expert to inspect the site and determine the actual percentage of completion, to match the executed works against the drawings and specifications, to reconcile what the contractor received against what he earned, and to assess the cost of completing the remaining works. The quality of the documents you place before the expert — the contract, drawings, bills of quantities, payment receipts, correspondence and dated site photographs — is what practically shapes the outcome of the case.
When does the matter turn into a criminal complaint?
As a rule, stopping performance of a construction contract is a civil dispute resolved through termination, compensation and completion at the contractor’s expense, and it is not in itself a crime. However, the facts may be accompanied by separate acts criminalised under the Crimes and Penalties Law, such as obtaining money by fraudulent means or by assuming a false name or an untrue capacity, or disposing of sums or materials delivered to the contractor for a specific purpose in a manner contrary to that purpose.
Whether an offence is established is a matter for the Public Prosecution and the criminal courts according to the facts and evidence of each case. It is therefore unwise to file a criminal complaint on an impressionistic basis, since the shelving of the complaint may later be used against you before the civil court. The correct characterisation of the facts should first be studied with a specialised lawyer.
After the building is completed: the decennial liability
The end of the dispute with the defaulting contractor does not end your future rights. The Civil Transactions Law imposes on the engineer and the contractor a guarantee for a period of ten years covering total or partial collapse of what they have constructed or of fixed installations they have erected, and any defect appearing in them that threatens the strength and safety of the building. Documenting the date of final handover and preserving the drawings and handover reports therefore remains essential even after the project ends.
Dates and figures to keep in mind
| 1 June 2026The date on which the Civil Transactions Law issued by federal decree-law and published in the Official Gazette on 14 October 2025 came into force | 10 yearsThe period of the engineer’s and contractor’s guarantee against total or partial collapse or any defect threatening the strength and safety of the building |
| Reasonable periodThe period granted to the contractor in the notice to correct or resume the works before seeking termination or authorisation to complete at his expense | ImmediatelyThe timing for applying to establish the site condition, before the site is altered or a new contractor is brought in |
Practical tips
1- Do not rely on verbal promises; document every demand to resume work by a written letter or a preserved email.
2- Do not pay advances outside the payment schedule tied to completion milestones. Linking payment to progress is the strongest practical protection in this type of contract.
3- Photograph the site periodically with clear dates from the very start of the project; those photographs become decisive evidence before the expert.
4- Verify that the contractor’s licence and activity are valid with the licensing authority, and that the contract details match the licensed trade name.
5- Keep a copy of the contract, drawings, bills of quantities and all annexes and variations signed by both parties.
6- Consult a specialised lawyer before serving the notice, because the drafting and content of the notice determine the strength of your position in any subsequent claim.
Legal references
1- Federal Decree-Law No. 25 of 2025 promulgating the Civil Transactions Law.
2- Federal Decree-Law No. 42 of 2022 promulgating the Civil Procedure Law.
3- Federal Decree-Law No. 31 of 2021 promulgating the Crimes and Penalties Law and its amendments.
4- Federal Decree-Law No. 50 of 2022 promulgating the Commercial Transactions Law.
Frequently asked questions
Our legal services in Dubai
AWADH ALMHEIRI LAW FIRM AND LEGAL CONSULTATIONS provides specialised legal services in construction contract disputes in the Emirate of Dubai, including cases where a contractor stops completing villas and buildings, drafting notices through the Notary Public, applications to establish the site condition and appoint experts, claims for termination of the construction contract and for authorisation to complete at the contractor’s expense, and claims for compensation and delay penalties before the courts of Dubai at their various levels.
Our services in the rest of the Emirates
The scope of these services extends to the rest of the country, including Abu Dhabi, Sharjah, Ajman, Umm Al Quwain, Ras Al Khaimah and Fujairah, assisting villa and project owners to complete their suspended works, settle accounts with defaulting contractors, have recourse to financial securities, and protect their guarantee rights after handover.


